BI treated same as other futures T facilities in 3 scenarios
Cost of BI included in T analysis in next phase
In Phase II, BI facilities may be replaced by more optimal T for final scenarios.
EISPC Presentation on BI
BI will impact gen picked in Phase I
Goal: include infrastructure reasonably certain to be built. Initial include bucket - 12/31/15 - reliability and existing, under construction, state budget approved or planned. Exclude others and subject to petition process. Beyond 2016 petition. Standard is reasonable certainty. WECC used petition process.
Advantages: apples to apples. increase confidence in results.
Proposal B
2010 -2015 include all. 92% are reliability. 74% of gen projects are planned.
Results in a more manageable process according to its proponents.
SSC would vote to include or exclude based on PA replies after a challenge session (what is purpose/need for project; what concern is raised re: transfers if project approved)
Proposal C
If take too much out, model won't solve. 2010- 2015 all in. But all subject to petition process. Can tak out if not reasonably certain to be built. 2016- 2020 all out unless put in by petition.
Higher standard for gen. If in doubt, leave out.
Public Power. include up to 2015. include after 2015 if reliability or planned or within a PA. no petitions. focus on interregional planning.
TO: concern about petition process, concern about bottom up v. top down. all T and G reliability and planned til 2015 in. all reliability and planned T included to 2020 included but petitions for other types. focus on interregional impacts of projects. PA should have role.
Gens: concern about getting to closure quickly. start with roll up. 1st five years frozen. for 2015-2020 discussion should be whether it should come out. do not want subjective process.
NGO: want things in current law (RPS) facilitated. Starting point is current law. Do not want to spend alot of time in the weeds or on lengthy petition process. Want to see costs of BI choices.
Alt Suppliers: Besides PAs, others have not said why its important to be careful about whats in.
States: admin ease cannot be more important to accuracy of baseline. ensure results we get from futures is not skewed by baseline infrastructure that is not reasonably certain.
Recent Comments